Answer: TGERC has finalized the pre-levelized tariff for Rs. 3.13/Kwh under PM KUSUM component A scheme.
Answer: The Tariff is fixed for 25 years.
Answer: Tariff in Power Purchase Agreement (PPA) is fixed for 25 Years and it cannot be altered.
Answer: A Letter of Credit (LC) is available for payment security.
Answer: The DISCOM will release payments immediately after receiving the physical copy of the invoice from the Solar Power Generator (SPG).
Answer: If the DISCOM delays payment beyond 30 days from the due date, a late payment surcharge of 1.25% per month on the outstanding amount shall be applicable, calculated on a day-to-day basis.
Answer:
Answer: No permission required for land-use
Answer: Model lease agreement already provided in www.pmkusum.telangana.gov.in
Answer: Net SGST: 50 % Reimbursement on COD, Exemption of NOC from PCB, reimbursement of DISCOM supervision charges, Stamp duty and water charges, 100 % exemption of Electricity Duty
Answer: Yes. Its valid for 25 Years
Answer: Yes, it is clearly mentioned in the PPA.
Answer: Yes, all the finalized applicants those who received Letter of Award (LOA) should pay Rs. 1 Lakh/MW valid up to 15 Months the same will be returned after the COD
Answer: Developers are required to submit a Net Worth Certificate of Rs. 1 Crore per MW. However, there will be no financial eligibility criteria for farmers.
Answer: No, it is responsibility of the developer (SPG) to get insured of the plant.
Answer: The commissioning shall be completed on or before 31-12-2025
Answer: Deputy General Manager (Technical), TGREDCO, Mob:6304903933